The Manchester evening news broke the story today that people in Islington Wharf Mews are being told that they will have to leave their homes for a good part of a year.
People are being forced to move out of a brand new city centre apartment block – because it breaks fire safety rules. Many of the residents in Islington Wharf Mews, on the edge of the city centre, had only bought their waterside properties last year.
But it soon emerged that their newly-built homes were not properly fireproofed. The M.E.N. understands they now have to move out for up to 10 months while the defect is fixed.
Yes ISIS waterside development hadn’t fireproofed the new apartments to the safety standards required by law!
This is frankly not only shocking but a total disgrace; putting many peoples lives in danger. I’m glad this was discovered or revealed before something happened and people died!
Of course as a home owner of ISIS waterside’s Islington Wharf (phase 1) I’m happy to finally see some press attention about the on going shocking state of the heat gain problem in the apartments. This was not taken lightly, with the worry about the affect on property value of course.
Meanwhile the same developer – ISIS Waterside – is also embroiled in a row with people living in the first phase of the development next door. People living in Islington Wharf, which was built in 2008, say they are considering legal action because temperatures soared to more than 35C in their flats every summer. The developer is planning to replace the windows and temporary air conditioning units have been handed out.
This is also pretty much true, its the number one reason why people leave the apartments. We have seen reports of things melting into sofas and temperature reports with photographic evidence of closer to 40c a few years back (we have them backed up). Yes its nice not having to put the heating on in winter but at least my flat is liveable in summer. Some residents have rooms with no chance to open windows!
There have been many tests, and I even had some equipment in my flat testing the heat in the past. Every-time, they (ISIS and others) all pretty much agree something needs to be done. However the proposals to the committee (which I am a part of) have been poor, short-sighted and full of holes.
The air conditioning units were/are temporary till a sustainable long term solution is found. The committee will not be pushed into a solution which ultimately is bad for everybody involved (we have meeting minutes also backed up), but we have been working very hard to make this a reality.
Its worth saying a few things…
The heat problem affects roughly half of Islington Wharf, I’m not affected as my flat faces the sun in the morning and evening only (by pure chance not by design or choice). Islington wharf has had many problems in the past including the terrible communal boiler system, but things have gotten better with a new management company, Revolution.ISIS have been granted approval to build the 3rd phase of Islington Wharf, very much against the Islington Wharf committees support and many of the residents.Its my view that, their track record across Islington Wharf Mews, Granary Wharf (I remember their was a serious problem a few years back, but cant find anything about it now, maybe results have been removed?) and of course Islington Wharf. Should be a clear sign to put the 3rd phase on hold till the other issues are actually sorted out and the residents are happy. No matter what Nigel Franklin, Director of ISIS Waterside Regeneration thinks or says…